Additionally, it is expected that the ball mill will be set in place in December 2023, ahead of schedule, allowing the focus for the start of 2024 to shift to piping and mechanical systems. Progress to date has considerably derisked the Goose Project. ... the Goose Project capital cost being approximately C800 million, and total capital ...